• Compliance of the site with disabled people accessibility, with the creation of a Main Pedestrian Vertical Circulation (CVPP) with an elevator serving the 6 levels as well as the surface.
• Creation of a new customer reception area and new operating premises for agents.
• Complete takeover of the park’s electrical installation with the implementation of a transformer in place of the existing Yellow Tariff.
• Complete overhaul of the parking platforms, including:
• Complete painting,
• Implementation of a sprinkler network,
• Complete resumption of smoke extraction to bring it up to standard,
• Replacement of existing lighting with LED lighting,
• Replacement of locksmith / metalwork equipment.