ROUXEL STORE (MODULAR ERP BUILDING TYPE CTS OF 850M2)

  • PLAINE COMMUNE DÉVELOPPEMENT

    Client

  • NR ARCHITECTURE

    Architect

  • 2017 / 2018

    Production

  • 6 MONTHS

    Duration of works

  • 1 160 K€

    Budget

  • Mission

    Full project management asbestos removal, demolition and construction

WORK

Asbestos removal and demolition of a set of buildings and a garage

Realization of general earthworks and various networks

Realization of the foundations of the structure

Quartz casting concrete slab on 1 100m2 and creating parking in asphalt

Assembly of a temporary frame in aluminum frame, sandwich panel facades, insulated roofing

Facilities: interior lighting, “strong” and “weak” currents, reversible air conditioning