BUS CENTER MONTROUGE – CORENTIN SITE (75)

  • SEDP

    Customer

  • 2018 / 2019

    Realization

  • 6 MONTHS

    Duration of work

  • 1,1 M€ HT

    Budget

  • Mission

    Project management

WORK

    • Realization of premises intended to accommodate the electrical equipment necessary for the bus power supply (transformers, HTA cells, etc.)
    • Adaptation of storage and workshop to allow the passage of electrical equipment ensuring the load of buses:
      • Network outsourcing (Plumbing, SSI, CFO-CFA, Sprinkler)
      • Core drilling, drilling, hoppers
      • Implementation of metal hangers