DEVELOPMENT OF BORDS DE MARNES

Nogent sur Marne (94)

  • Communauté d’Agglomération de la Vallée de la Marne

    Client

  • Atelier Jacques Coulon Paysage

    Landscaping

  • 18 mois –Reception of works Septembre 2013

    Duration of work

  • €3 100 000,00

    Budget

  • Mission

    BET – Landscaping contractor Jacques Coulon

WORK

Development of the edges of Marne to ensure the continuity of a path of gentle traffic between the railway viaduct of Nogent-Le Perreux to the Bois de Vincennes.

Realization of esplanades at the level of the island of beauty offering bleachers and solariums descending full south on the Marne.

Latest achievements